• City proposes improvements to Trillium Line extension south

    Ottawa – Mayor Jim Watson announced today a new alignment for the O-Train Trillium Line extension as part of the Stage 2 Light Rail Transit project.

    The new alignment would move Bowesville Station to the edge of the urban boundary just southeast of the Bowesville and Earl Armstrong intersection, bringing rail almost a full kilometre closer to the Riverside South community. The new alignment also takes advantage of an existing City-owned rail corridor, ultimately reducing the environmental impact on sensitive green spaces, in addition to reducing potential land costs and simplifying construction.

    This new Earl Armstrong/Bowesville station and alignment also facilitates a potential future extension to Limebank Road to better integrate with the community of Riverside South as it grows. This potential future extension to Limebank requires an amendment to the existing Environmental Assessment for the Trillium Line, as well as a targeted update to the Community Design Plan for Riverside South. City staff will be completing these updates over the summer.

    The Trillium Line extension is one of the three extensions in Ottawa’s Stage 2 project package. In the South, the Trillium Line will be expanded to reach Bowesville Station with a link to the Ottawa Macdonald-Cartier Airport by 2021. In the East, the Confederation Line will extend to Trim Road by 2022. In the West, rail will reach Algonquin College and Moodie Drive by 2023.

    Once complete, Stage 2 will bring 70 per cent of Ottawa residents within five kilometers of fast, efficient, clean and reliable rail with the capability of carrying an estimated 24,000 riders per hour per direction during peak periods. The complete O-Train system will span 60 kilometres and include 41 stations.

    For more information on City programs and services, visit ottawa.ca or call 3-1-1 (TTY: 613-580-2401). You can also connect with the City through FacebookTwitter and Instagram.

    City of Ottawa secures funding for Stage 2 LRT

    Province of Ontario invests $1.16 billion into Phase 2. That’s billion with a “B”

    Quotes

    “The new proposed alignment will bring thousands of residents closer to rail and have a reduced impact on environmentally sensitive Greenbelt lands. In Riverside South alone, the City is forecasting a residential growth of nearly 15,000 households or approximately 40,000 people over the course of the next ten years.”
    Mayor Jim Watson, City of Ottawa

    Quick Facts:

    • Confederation Line (Stage 1)
      • Length – 12.5 km
      • Downtown tunnel – 2.5 km
      • Number of stations – 13
    • Stage 2 (Confederation Line and Trillium Line)
      • 24,000 people per direction per hour at peak capacity
      • 39 km of new rail
      • 23 new stations
      • South extension
        • 12 km including a spur to the Airport
        • 7 new stations
        • Completion 2021
      • East extension
        • 5 km
        • 5 new stations
        • Completion 2022
      • West extension
        • 15 km
        • 11 new stations
        • Completion 2023

    Website
    Stage 2
    Confederation Line
    Ready for Rail
    OC Transpo

    Social media
    Facebook
    Twitter
    Instagram

  • City of Ottawa secures funding for Stage 2 LRT

    Ottawa – Mayor Jim Watson was pleased to welcome Prime Minister Justin Trudeau to the Belfast Yard Maintenance and Storage Facility today, where the Government of Canada announced its financial support for the Stage 2 LRT project.

    The federal government has pledged to contribute up to $1.09 billion in total eligible costs to Stage 2 through their long term plan, Investing in Canada. This is in addition to the over $67 million the federal government committed to Stage 2 through the first phase of the Public Transit Infrastructure Fund last year.

    Mayor Watson and Prime Minister Trudeau were also joined by Infrastructure Minister Bob Chiarelli from the Province of Ontario, which has already promised to invest $1 billion towards Stage 2 LRT, plus 50 per cent of the cost associated with extending the O-Train system to the Ottawa airport and from Place d’Orléans to Trim.

    The remainder of the LRT costs, approximately $1 billion, will be covered by the City of Ottawa.

    In the South, the Trillium Line will be expanded to reach Bowesville Station, with a link to the Ottawa Macdonald-Cartier Airport, by 2021. In the East, the Confederation Line will extend to Trim Road by 2022. In the West, it will reach Algonquin College and Moodie Drive by 2023.

    Once complete, Stage 2 will bring 70 per cent of Ottawa residents within five kilometers of efficient, clean and reliable rail service with the capability of carrying an estimated 24,000 riders per hour per direction during peak periods. The complete O-Train system will span nearly 60 kilometres and include 41 stations.

    The confirmed federal and provincial funding allows the City to move forward with its innovative procurement solution for the Stage 2 extensions, including issuing the Request for Proposals for the extensions of both the Confederation and Trillium Lines, as well as ordering the additional vehicles required to service the expanded system.

    Quotes

    “Today’s announcement puts the final piece in place for the funding of the Stage 2 LRT project. We can now plan to put shovels in the ground in 2019 as we continue expanding our world-class LRT system. Building Stage 2 will not only create jobs during construction, it will also give Ottawa a competitive edge to attract talent and new businesses to our city once the project is complete.”
    Mayor Jim Watson, City of Ottawa

    “Stage 2 will change the way commuters travel around the city. It will save you time and get you to work and home faster, expanding the reliability, accessibility and comfort of light rail transit. It will save residents money with reduced car costs, including fuel costs, vehicle wear and tear and even accident avoidance. It will take 14,000 vehicles off the road during rush hour and reduce greenhouse gas emissions by 110,000 tonnes and air contaminants by 3,000 tonnes every year.”
    Councillor Stephen Blais, Chair, Transit Commission

    Quick Facts:

    • Confederation Line (Stage 1)
      • Length – 12.5 km
      • Downtown tunnel – 2.5 km
      • Number of stations – 13
    • Stage 2 (Confederation Line and Trillium Line)
      • 24,000 people per direction per hour at peak capacity
      • 38 km of new rail
      • 23 new stations
      • South extension
        • 11 km including a spur to the Airport
        • 7 new stations
        • Completion 2021
      • East extension
        • 5 km
        • 5 new stations
        • Completion 2022
      • West extension
        • 15 km
        • 11 new stations
        • Completion 2023

    Website

    Stage 2
    Confederation Line
    Ready for Rail
    OC Transpo

     

  • Council approves Stage 2 plan to build rail to east, west and south

    Ottawa City Council today approved moving ahead with the Stage 2 project to bring light rail transit farther and faster to communities in the east, the west and the south.

    The Stage 2 report approved by Council includes recommendations changing the scope of the light rail transit (LRT) project, the procurement model and the specific activities the City will undertake to implement Stage 2.

    An expansion of the scope of the Stage 2 LRT Project was approved, including construction of an additional Maintenance and Storage Facility in the Moodie Drive area, final alignment changes and the following extensions to train lines:

    • Confederation Line West: beyond Bayshore to Moodie Drive, and southwest to Algonquin College;
    • Confederation Line East: beyond Place d’Orleans to Trim Road;
    • Trillium Line extension south to Bowesville in Riverside South; and
    • An Airport Rail Link from South Keys Station on the Trillium Line.

    The budget for the Stage 2 LRT project remains $3 billion, as approved in 2015. The new Moodie Extension is included within the original budget, while the Trim and Airport Extensions are conditional on receiving 100 per cent federal and provincial funding.

    Several related infrastructure works, such as widening of Highway 417 between Highway 416 and Maitland Avenue, are being bundled with Stage 2. This will improve construction integration, reduce detours, save money and reduce impacts to the community. The Stage 2 project will generate more than 21,000 person-years of employment.

    The City will continue to work with its existing partner, Rideau Transit Group, to ensure an integrated and consistent expanded rail system while maximizing the amount of work to be procured under new competitions.

    The Stage 2 expansion of the O-Train network will be undertaken through two new procurements:

    • A new $2.5-billion Design-Build-Finance competition for the Confederation Line East and West extensions (includes Airport, Trim and Highway 417, and City-bundled works); and
    • A new $535-million Design-Build-Finance-Maintain competition for the Trillium Line extension to the south.

    With this Council approval, the project can go to market later this winter. A final Council report will be brought forward in early 2018 outlining the results of the procurement process and related activities, leading to the final design and beginning of construction. The Stage 2 project is planned to proceed with staggered openings to allow for faster expansions to LRT service:

    • Trillium Line South extension in 2021
    • Confederation Line East including Trim in 2022
    • Confederation Line West to Moodie by 2023
  • Public Information Session on Stage 2 LRT

    Residents are invited to participate in an online interactive public information session on the Stage 2 Light Rail Transit (LRT) project, the largest infrastructure project in the City’s history, where they will have the opportunity to ask questions in person or via Facebook Live.

    On Wednesday, March 1, at 6:30 p.m., City staff will deliver a presentation on the Stage 2 LRT project before taking residents’ questions. The presentation will be broadcast live on the City of Ottawa’s Facebook page, where residents can post questions during the session as part of an online question-and-answer period. They will also be able to view the public information session on the City’s YouTube channel.

    Residents can attend in person at one of the following locations:

    • Main event: Champlain Room, Ottawa City Hall, 110 Laurier Avenue West, beginning at 6:30 p.m.
    • Satellite event: Hunt Club-Riverside Park Community Centre, 3320 Paul Anka Drive – hosted by South end Councillors, beginning at 6 p.m.

    Simultaneous translation will be available at the City Hall location. For more details, please visit ottawa.ca

    Please request any disability-related accommodation requirements by calling 613-580-2424, extension 44211 or email Jennifer.Charles@ottawa.ca.

     

  • City shares significant news about plans to move forward with Stage 2 Light Rail Transit

    Ottawa – Mayor Jim Watson, Councillor Keith Egli, Chair of the City’s Transportation Committee, Councillor Stephen Blais, Chair of the Transit Commission, and City of Ottawa staff today shared significant news about plans to move forward with the Stage 2 Light Rail Transit Project.

    City Staff also provided a detailed presentation of a related report on Stage 2 LRT, in advance of the tabling of the report at the Finance and Economic Development Committee on February 24, and at City Council on March 8. The briefing included an update on significant changes to the scope of the project, information on the final alignment adjustments, the recommended procurement model and the specific activities the City will undertake to get ready to implement Stage 2.

    Following extensive public consultation and preliminary engineering work, an expansion of the scope of the Stage 2 LRT Project is being proposed, in order to extend light rail further and faster to the West, South and East:

    • Confederation Line West: beyond Bayshore to Moodie Drive, and southwest to Algonquin College;
    • Confederation Line East: beyond Place d’Orleans to Trim Road;
    • Trillium Line extension to Bowesville and Riverside South; and
    • An Airport Rail Link from South Keys Station on the Trillium Line.

    As part of the Western Line extension, an additional Maintenance and Storage Facility will be built in the Moodie Drive area to continue to fast-track LRT progress westerly and service the 8,500 public servants at the new Department of National Defence employment hub at the former Nortel Networks campus.

    The briefing also laid out the City’s innovative approach to the procurement of the Stage 2 Project, continuing to work with existing partner Rideau Transit Group (RTG) to ensure an integrated and consistent expanded system while maximizing the amount of work to be procured under new competitions.

    The Stage 2 expansion of the O-Train network will be undertaken through two new procurements:

    • A new $2.5-billion Design-Build-Finance competition for the Confederation Line East and West extensions (includes Airport, Trim and Highway 417, and City-bundled works); and
    • A new $535-million Design-Build-Finance-Maintain competition for the Trillium Line extension.

    The $3 billion in light rail contracts will be bundled with additional City infrastructure projects in order to improve construction integration, reduce detours, save money, and reduce impacts to the community. The total of over $3.6 billion in combined work will generate over 21,000 person-years of employment.

    Upon approval of this report by Council, the project will go to market later this winter. A final report will be brought forward in early 2018 outlining the results of the procurement process and related activities, leading to the final design and beginning of construction. The Stage 2 project will proceed with staggered openings to allow for faster expansions to LRT service:

    • Trillium Line South extension in 2021
    • Confederation Line East including Trim in 2022
    • Confederation Line West to Moodie by 2023

    Quotes

    “In 2013, Council set out an ambitious goal for our City: to extend and share the benefits of light rail to more people in Ottawa by going farther and faster to the South, East and West. Today, staff delivered a report that, once approved, will transform Ottawa’s LRT network into a world-class transit system. I look forward to continuing to collaborate with our Federal and Provincial partners on this important environmental transportation vision.”
    Mayor Jim Watson, City of Ottawa

    “Thanks to the experience and knowledge gained through the construction of Confederation Line, we are on track to the next stage of delivering a world-class transit system to our residents. When Stage 2 is fully complete in 2023, we will have added over 38 kilometres of new rail and 23 new stations to Ottawa’s transit system.”
    Councillor Keith Egli, Chair of the Transportation Committee

    “Over the next few years we will see our vision of a city-wide affordable transit system becoming reality, with this transformational investment in light rail increasing the quality and reliability of our service. More and more people will opt for transit as their first transportation choice, and not just for their daily commute, but for trips out with their families, to the game, the theatre – and not just to downtown.”
    Councillor Stephen Blais, Chair of the Transit Commission

    Quick Facts:

    • The Stage 2 Implementation report provides recommendations that meet the directions given by Council in the “Stage 2 Light Rail Transit (LRT) Environmental and Functional Design Report,” approved by City Council on July 8, 2015. If approved, it will allow for a competitive procurement process for all three Stage 2 extensions and the related supporting projects, and permit the projects to be built within the City’s affordability envelope.
    • The Stage 2 LRT Project budget is $3 billion (excluding the Trim Extension with one station at $160 million, and the Airport Rail Link with two stations at $155 million).
    • The Trim and Airport extensions will only proceed if they are fully funded by the federal and provincial governments; on June 3, 2016 the province of Ontario has committed to covering half of the capital costs for both of these projects.
    • Once the federal funding commitment is confirmed, the City can proceed with the release of the Stage 2 Request for Proposals.
    • The Moodie extension is expected to be achievable within the original budget envelope for Stage 2.

     

  • Historic transit win for Ottawa residents

    On June 3, the Province of Ontario announced an investment of $1 billion towards the City’s Stage 2 LRT initiative, plus 50 per cent of the cost associated with extending the O-Train system to the airport and from Place d’Orléans to Trim. This is a total investment of $1.16 billion. This is an historic vote of confidence in the future of the City of Ottawa.

    This is also the single largest one-time infrastructure investment by the Province of Ontario in the economic transformation of our city.

    My stated goal as Mayor of the City of Ottawa, working with my Council colleagues, is to ensure that we continue to expand our LRT system to meet the needs of our residents – we don’t want to put shovels away in 2018 once the Confederation Line is complete.

    With the Province’s support, we can keep building on this momentum as we work to extend LRT farther west to Bayshore and Algonquin College, even farther east to Trim, and farther south to Riverside South and to the Ottawa Airport.

    The Province’s investment strengthens our ability to deliver a reliable, world-class, environmentally sustainable LRT system.

    By reducing traffic congestion and better connecting our city, this project will support our region’s economic success – boosting Ottawa’s competitive edge and the ability of local firms to compete with the world, while welcoming a greater number of visitors from around the globe with a modern light rail system that will enhance the visitor experience in our magnificent city.

    Stage 2 will see us further expand Ottawa’s O-Train network to a system with more than 50 kilometres of rail. The reach of this investment will bring 70 per cent of the city’s population to within five kilometres of a station by 2023.

    This is a game-changer for Ottawa – for our local economy, for our environment, for spurring smart growth, and for our quality of life.

    It will provide fast, comfortable and convenient connections between our residential areas, our largest employment areas, major retail outlets, and key cultural and recreational destinations.

    It will also support our efforts to build an education and innovation powerhouse, anchored by our four post-secondary institutions – the University of Ottawa, Carleton University, Algonquin College and La Cité Collégiale.

    As for improving the quality of life for our Ottawa residents – we know an hour spent in gridlock is an hour away from family and other much more productive endeavours.

    Stage 2 will take more than 10,000 cars off the road, it will dramatically reduce the number of buses on our streets and roads, and will help fight gridlock in our fast-growing city.

    The system will integrate stations into the urban fabric of our neighbourhoods and will improve walking and cycling, as well as providing a transit system that is accessible to all.

    Friday’s funding announcement symbolizes the progress we have made as a city.

    I am very proud that Council unanimously carried the proposal to build the Confederation Line, followed by the unanimous decision to build Stage2.

    Without that teamwork, we would not be here today.

    I am also proud of the tremendous support we have received from the people of Ottawa since launching our proposal to bring LRT to Ottawa and to build it with a downtown tunnel.

    Demand for LRT is growing across our city as residents seek a sustainable alternative to the worsening gridlock.

    Ottawa used to be the laughing stock of the province after north-south rail was cancelled. That is no longer the case.

    We are moving forward with a bold plan with the unwavering support of the Province of Ontario. In the coming months, we will work with the Government of Canada to secure their contribution to Stage 2 LRT as well.

    My commitment to the residents of Ottawa is to stay the course and pull out all the stops to see this vision through.

    The Province’s funding commitment is a very important stop en route to our goal of building a world-class transit system for the residents of Ottawa.

     

  • Ontario Committing More Than $1 Billion for Stage 2 LRT in Ottawa

    Today, the Province of Ontario announced more than $1 billion in funding towards the City of Ottawa’s Stage 2 LRT expansion project. This historic investment in our City will boost our economy, connect our city and improve the quality of life of residents.

    Read the official Province of Ontario News Release below


     

    News Release

    Ontario Committing More Than $1 Billion for Light Rail Transit in Ottawa

    June 3, 2016

    New LRT Will Create Jobs, Drive Growth and Improve Quality of Life

    Ontario is committing more than $1 billion toward the City of Ottawa’s Light Rail Transit (LRT) expansion project to help grow the economy, reduce travel times and connect people to jobs.

    Premier Kathleen Wynne announced the investment in Ottawa today. The funding represents the largest provincial transit investment in Ottawa’s history. New, modern light rail vehicles on tracks separated from regular traffic will offer fast, efficient service and improve travel for people across the region. The expanded LRT will also lower greenhouse gas pollution, improving air quality and fighting climate change.

    The Stage 2 LRT project will add 30 kilometres of new rail and 19 new stations, extending the LRT network to the east, west and south. Ontario’s funding commitment will also help support the capital costs of two additional extensions: a spur to the Ottawa Macdonald-Cartier International Airport and an extension to Trim Road in Orléans. These will add 6.5 kilometres of new rail and three stations. Construction on Stage 2 is expected to start in 2018, once the Stage 1 Confederation Line is completed. Stage 2 is expected to enter service in 2023.

    Ontario’s funding for Stage 2 is part of the largest investment in public infrastructure in the province’s history — $160 billion over 12 years — for projects such as roads, bridges, transit systems, schools and hospitals. The planned investments would support 110,000 jobs on average every year across the province. In 2015, Ontario announced support for more than 325 projects that will keep people and goods moving, connect communities and improve quality of life.

    Investing in priority transit infrastructure is part of the government’s economic plan to build Ontario up and deliver on its number-one priority to grow the economy and create jobs. The four-part plan includes investing in talent and skills, including helping more people get and create the jobs of the future by expanding access to high-quality college and university education. The plan is making the largest investment in public infrastructure in Ontario’s history and investing in a low-carbon economy driven by innovative, high-growth, export-oriented businesses. The plan is also helping working Ontarians achieve a more secure retirement.

    Quick Facts

    • Ontario has already committed up to $600 million towards the Stage 1 LRT project, called the Confederation Line — a $2.1 billion project that is jointly funded with the Government of Canada and the City of Ottawa.
    • Stage 2 will extend the Ottawa LRT network to the east from Blair to Place-d’Orléans Station; to the west from Tunney’s Pasture to Bayshore Station and southwest to Baseline Station; and to the South from Greenboro Station to Bowesville in Riverside South.
    • Ontario’s commitment of more than $1-billion will also support two additional extensions, a two-stop spur from the Trillium Line to Ottawa Macdonald-Cartier International Airport, and a one-stop extension of the Confederation Line further east from Place-d’Orléans Station to Trim Road in Orléans.
    • Construction is expected to generate nearly 24,000 person-years of employment, or nearly 1,000 full-time jobs.

    Additional Resources

    Quotes

    “Our investment in the Ottawa LRT will make a big difference in people’s everyday lives. It’s one of a number of historic investments in infrastructure that our government is making. It will help to create jobs and grow our economy now and for years to come.”
    — Kathleen Wynne, Premier of Ontario

    “The province remains committed to working with the City of Ottawa as it moves forward with implementing its Stage 2 LRT project. We know how important public transit is to managing congestion, curbing emissions, creating jobs and building communities.”
    — Steven Del Duca, Minister of Transportation

    “Ontario’s funding of Stage 1 and now Stage 2 of LRT is a major contribution to the economy and quality of life of Canada’s capital city; an efficient and complete transit system is a necessity for our dynamic city.”
    — Bob Chiarelli, MPP for Ottawa West-Nepean

    “This is the largest one-time infrastructure investment‎ by the province of Ontario in the economic transformation of our city. On behalf of the City of Ottawa, I would like to thank the Honourable Kathleen Wynne, Premier of Ontario, and local caucus members for this historic vote of confidence in Ottawa’s future.”
    — Jim Watson, Mayor, City of Ottawa

  • City of Ottawa and partners launch Stage 2 LRT funding request

    Stage 2 LRT – Mayor’s Message from Ottawa Light Rail on Vimeo.

     

    Ottawa – Mayor Jim Watson, Council members, and representatives from Ottawa’s business, tourism and academic communities have united together to officially launch the City’s LRT Stage 2 funding request to the federal and provincial governments.

    The Stage 2 project will further reduce commute times by adding 19 new stations and 30 kilometres of rail to Ottawa’s O-Train system between 2018 and 2023. From an economic standpoint, the project is expected to generate 24,000 person-years of employment, increase tax revenue to approximately $170 million, and provide an economic output of $3.8 billion to the local economy.

    “We are asking our provincial and federal counterparts to continue the great partnership we have established with the Confederation Line,” said Mayor Watson. “It is our hope that our partners will maximize their contributions to the project so we can continue the momentum, and proceed swiftly and confidently with Stage 2 of LRT.”
    The City of Ottawa’s funding request is supported by several Stage 2 LRT Project Champions, including the Ottawa Chamber of Commerce, the Orléans Chamber of Commerce, Ottawa Tourism, Ottawa MacDonald-Cartier International Airport, the Ottawa-Gatineau Hotel Association, Ottawa Festivals, Algonquin College, Invest Ottawa and several Business Improvement Areas.

    In addition, a recent business growth survey by the Ottawa Chamber of Commerce indicated that 74 per cent of business owners feel that Ottawa’s LRT expansion will have a positive impact on their business.

    “Stage 2 of LRT will make Ottawa an even more attractive city to create and grow a business,” said Ian Faris, of the Ottawa Chamber of Commerce. “Ottawa is the only G7 capital without a rapid rail system. We need to keep our economy moving by making this smart investment in our future prosperity.”

    “Reliable transportation is always a key success factor for attracting visitors and major events,” said Geoff Publow, Chair of Ottawa Tourism. “Stage 2 of LRT will make it easier for visitors to explore our beautiful city.”

    “Stage 2 of LRT will keep Algonquin College students moving for years to come – both from their homes to their classes, and from our campus to their work and co-op placements,” said Laura Stanbra, Vice President of Student Services at Algonquin College. “This expanded transit service will additionally provide residents with easier access to our student-run learning companies, programs, and services. We are delighted to serve as a Stage 2 Rail Champion and add our full support to the City’s proposal.”

    It has been recently confirmed through Environmental Assessment work that Stage 2 can be constructed within the $3-billion budget that was established in the City’s 2013 Transportation Master Plan. The project would extend Ottawa’s O-Train system:

    East: Extend the Confederation Line east from Blair to Orléans, with stations at St.Joseph, Jeanne D’Arc, Orléans Drive, and Place d’Orléans.
    West and southwest: Extend the Confederation Line west to Algonquin College and Bayshore, with stations at Westboro, Dominion, Cleary, New Orchard, Lincoln Fields, Queensview, Pinecrest, Iris, Baseline and Bayshore.
    South: Extend the O-Train to Riverside South and Bowesville, with a new station at Gladstone, and stations at Walkley, South Keys, Leitrim and Bowesville.
    When completed in 2023, Stage 2 would bring LRT to within five kilometres of almost 70 per cent of residents.

    For more information on Stage 2 of LRT, please visit stage2lrt.ca.

  • WLRT Corridor Recommendation

    I am writing to update you on the work undertaken by the NCC-City Working Group regarding the western light rail transit (LRT) corridor.

    I am pleased to inform you that the Working Group has reached an agreement in principle, which was announced at a joint press conference with the NCC this morning.

    This agreement meets all of the City of Ottawa’s objectives in its unanimously-approved Transportation Master Plan and will remain within our affordability plan for the project. We would also be able to keep our long-standing commitment to the community to protect the Byron Linear Park and Rochester Field while providing even better access to the waterfront.

    Background

    In late November 2014, I met with then-Minister John Baird to discuss our Stage 2 LRT project. At that meeting, we had a very constructive discussion about this important project. We agreed to a 100-day dialogue between the City and the NCC to find a mutually satisfactory solution for the western extension of the Confederation Line between Dominion and Cleary.

    In December, the City of Ottawa and the NCC formed a joint Working Group to address this issue. The City representatives on the Working Group were Transportation Committee Chair Keith Egli, Transit Commission Chair Stephen Blais, Bay Ward Councillor and Deputy Mayor Mark Taylor, and City Manager Kent Kirkpatrick.

    I want to thank Councillors Egli, Blais, and Taylor for their hard work alongside our City Manager and our partners at the NCC. This was a very intensive review process which was supported by technical and urban planning expertise, and one that led to a historic outcome today.

    I also want to thank Minister Pierre Poilievre for his leadership. He was named Minister Responsible for the NCC during this process and brought the same constructive tone as his predecessor to this important partnership.

    The solution

    The Working Group has recommended a solution that would allow the western LRT extension to be fully buried under realigned Sir John A. Macdonald Parkway lanes between Dominion and Cleary stations. You will be pleased to learn that this solution would remain within the City of Ottawa’s project budget envelope.

    This solution would bring many benefits for the City of Ottawa, the NCC, local residents, and indeed all Canadians:

    – Protection of the Byron Linear Park and Rochester Field;

    – Minimal visual impact on the landscape and experience by users of the corridor

    – Continuous access to the corridor lands and 38% more usable shoreline parkland

    – Improved cycling and pedestrian access via two new crossings under the Sir John A. Macdonald Parkway

    – Retention and enhancement of the mature forest, lands and landscaping elements

    – An eventual reduction of nearly 500,000 bus trips annually on the Sir John A. Macdonald Parkway

    Of course, these highlights are on top of the city-wide benefits of our larger Stage 2 LRT project, which includes 30 kilometres of rail and 19 new stations. We hope to break ground on this world-class project once the Confederation Line is operational in 2018, which will help us deliver reduced commute times, cleaner air, and a stronger economy.

    Into the future, this recommended route would perfectly complement the NCC’s vision to create a new linear park of national significance along the waterfront.

    Moving forward

    Residents will be able to provide public feedback as part of the public outreach activities planned for the Confederation Line west LRT extension Environmental Assessment (EA) process:

    Monday, March 30
    Evening (time to be announced)
    Ottawa City Hall
    Jean Pigott Place

    This will be an open house to review the 100 Day Working Group Solution between Dominion and Cleary Station.

    The NCC will discuss the solution and the results of the public consultation session at its Board of Directors meeting in April.

    The Transportation Committee and Council will have the opportunity to review and discuss the results of the EA processes for all Stage 2 projects, including the Confederation Line west extension in June. The EA report will provide a recommended alignment for each of the corridors based on a technical review and results of the public consultation sessions for these extensions.

    The materials presented today, including a visual of the proposed alignment can be found online at ottawa.ca/stage2.

  • Mayor’s Remarks: Stage 2

    CHECK AGAINST DELIVERY

    Thank you all for coming.

    I’ve invited you here today to talk about how our city will grow and the fundamental tool that public transit offers us for intelligent planning.

    And how – if we are smart – we can use our public transit investments to make sure our transportation system will serve Ottawa as we grow in the years to come.

    This Council began its term by fundamentally taking the reins on light rail.

    It had become clear that the project we inherited – the so-called cross-country, deep-dive route that had been planned – could not be constructed for the established budget.

    Any cost overrun would be very much our problem.

    The federal and provincial contributions were each capped at $600 million.

    Already the City would be shouldering $900 million of the $2.1 billion originally budgeted to complete the Confederation Line.

    So we knew, as a Council, that we needed to correct course – because we had to pay every penny of cost increases.

    The Confederation Line deals with the downtown bottleneck that is strangling productivity increases in the transit system.

    It lays the foundation for a move to broaden the benefits of Light Rail Transit and expand on the important project now under construction.

    Increasing costs on the Confederation Line would mean fewer resources available for these extensions.

    We simply could not allow the project to bloat.

    So we took action.

    It was about 10 months ago when we gathered in this room to unveil the final Confederation Line designs.

    The Queen Street alignment achieves a better transit result with shallower, more accessible stations.

    This, along with an innovative competition – one now being copied by other municipalities – brought the budget back into line.

    The result, obtained with the very successful design-build-finance-maintain contract signed last year, has since proven the importance of Council’s actions.

    We are finally going ahead with light rail.

    On time.

    On budget.

    Fixed price.

    Tunnel and all.

    With construction now underway, I could not be more proud of the result we achieved.

    This Council has put in place a new framework of fiscal prudence.

    Before we went ahead with the Confederation Line, Council commissioned a long-term affordability review of public transit.

    These operating costs continue to challenge us at budget time, so before starting with the Confederation Line we wanted to review our long-term financial model to ensure we had a strong plan.

    A plan – not just for the first stage of LRT – but also for stages to come.

    We set tough tests for this transit affordability review.

    We looked at everything we were planning to build under the current Official Plan for public transit over the next 38 years – including the Confederation Line – covering both capital and operating costs.

    We respected the 2.5% tax cap set by this Council.

    Transit fares were held to the rate of inflation.

    We did not allow any shifting of additional road moneys into public transit.

    I want to underscore that point – we did not change the balance of investment toward transit and away from roads – and with today’s TMP we continue with this same balance of roads and transit without allowing any shift.

    So the affordability test we established was very tough.

    And this is, by the way, the first time this kind of comprehensive review of Ottawa’s public transit affordability has ever been done.

    Further, this is the first time, that all of our City’s planning efforts are coming together at the same time:

    The Official Plan… Infrastructure Master Plan… and the Transportation Master Plan, which includes the pedestrian and cycling plans.

    These major planning efforts are interconnected, so it makes sense that we ensure synergy between them at such a crucial point in our city’s history.

    The Transportation Master Plan we will release later today has at its foundation all of the tough affordability tests we continue to apply to maintain the framework of fiscal prudence that we have all committed to on this Council.

    A framework that is fair for taxpayers and fair for transit users.

    So let me tell you how we’ve changed things to ensure we have a realistic plan… a plan that does not over-promise.

    And one that we can deliver while continuing to live within our means.

    First, we changed the way estimates are being done for projects.

    Too many tenders were coming in over the early estimates used in our financial planning.

    We are being more comprehensive in the estimate process now, so our early financial planning is more realistic.

    We changed the way these estimates come together to include ample contingencies.

    We now look at the earliest stage to include estimates for property and utilities that we realistically will have to cover.

    Second, we are placing an affordability lens on the planning choices right from the beginning.

    This is an innovation in realistic planning on which Ottawa is leading the way.

    We are proposing a TMP that, for the first time, fits within what we can afford and is built from the beginning to produce the biggest bang for the buck.

    Third, we have taken a far more conservative view of how much it will cost to run our transit system.

    We have built in the flexibility to match service with increased ridership and are assuming the highest cost scenario.

    We have been far more conservative about the fairbox revenue we have in the model, so we know we will do at least that well.

    We are taking this approach so that we have a solid base and when we do better at earning new transit riders, our budget picture will just improve.

    Rather than building a model that counts on future success, we will aim for better, but not count on better.

    So we have taken the affordability model for transit to the next step.

    The tough tests from our first affordability review are now buttressed further by even far more conservative assumptions.

    This is part of building a Transportation Master Plan that won’t over promise and under deliver.

    With that framework of financial prudence in place, today I am going to focus on the transit plan because it is so central to ensuring we can maintain excellent mobility.

    Later today, the joint Transportation Committee and Transit Commission presentation will provide more detail on the road, sidewalk and cycling plans also included in the TMP.

    It will be an integrated plan designed to improve our entire network and make our community more livable for the benefit all users.

    We will move ahead to complete needed improvements for the bus system.

    This includes a new Transitway from Bayshore to Moodie and from March to Terry Fox to connect Kanata.

    There will be new measures to speed buses in the east along Blair, connecting La Cité into our rail network as well.

    And we are fully funding these improvements without waiting any longer for federal and provincial contributions.

    In the TMP, you will see a host of transit priority measures to improve reliability and shorten travel times.

    These are all planned to be 100% municipally funded and not cost shared as they have been in past plans.

    So we have a strong bus package.

    We also have a strong cycling plan.

    We are focused on completing a network around the city so that more people can safely choose to take a bike where they are going.

    This means tackling key priority cycling links with improved facilities, leveraging our existing assets, and connecting missing links to community destinations across the city.

    Our cycling plan includes what many in our community and around the Council table have been looking for.

    Improving our road network is also a priority because realistically most of our trips are in personal vehicles.

    Let me give you a few examples.

    We will move quickly to increase traffic flows through key intersections along Prince of Wales – at Merivale, Fallowfield, Deakin, and at the Hunt Club bridge.

    After that, we will move to fix the log-jam north from there to Colonnade Road.

    We will also move on a major project – a four-lane extension of Greenbank from Cambrian to Jockvale.

    This will ease the bottleneck that currently exists and would otherwise increase with the opening of the new rec centre and as well as planned development further to the south in Manotick and Richmond.

    We will move quickly on the implementation of Chapman Mills Drive, the widening of Brian Cobourn from Navan to Mer Bleu, and the Kanata South Link widening.

    This will create more options for commuters to get in and out of these fast-growing communities in our south, east and west.

    We will also complete upgrades in areas where development has outpaced some parts of our road network such as sections of Klondike and Country Club Roads.

    Every Councillor will be pleased to hear that we will move quickly to restore predictable travel times on the Airport Parkway where it bogs down between Hunt Club and Brookfield with new HOV and taxi lanes.

    And our commitment to improve roads in rural areas is steadfast in this plan.

    I am confident we have a strong set of priorities for our roads projects funded largely by growth and development charges.

    The pedestrian plan will work on key links as well to recreation, schools, shopping, and leisure activities.

    We will review pedestrian safety where there are community concerns – as we’ve heard on Merivale Road and Scott Street.

    We will continue to build smarter streets as we rehabilitate older roads to include good pedestrian links and more safe cycling options.

    We will take our first steps to mainstreeting Cyrville.

    For the first time, the full capital plan includes an envelope for the funding of the pedestrian crossings, such as the bridge from Donald to Somerset for which several Councillors have been champions – including Councillors Clark and Fleury.

    Funding for these projects will be included in the draft budget later this month.

    And in addition to stand-alone projects, we will take a pragmatic and integrated approach to designing more complete streets – whether through growth or renewal – to better service all users and to make life on our streets more vibrant.

    Where roads can better serve and more effectively service pedestrians, cyclists or transit, we will do so, but only where there is value in doing so in a manner that is practical, flexible and prudent.

    Which leads us to the focus of my remarks this morning.

    Stage 2…

    Our plan to spread the benefits of light rail right across our city.

    Light rail transit is our most powerful smart growth tool.

    When we are clear as a city about where Light Rail rapid transit will be into the future… we have a powerful effect on how our city grows.

    Unlike a bus route, rail transit routes do not periodically change.

    So the community can plan.

    Businesses can plan.

    And we get smarter growth.

    The more quickly we move forward with strength and certainty on transit, the more attractive and reliable the system becomes.

    And as options increase, more families will choose transit over the expenses of buying a second car.

    Excellent public transit opens more possibilities for more people than you might think.

    So… let’s start our discussion of Stage 2 of LRT with how much our fiscal plan contains for public transit growth projects, as opposed to renewals.

    In previous TMPs, our plans for transit have assumed cost sharing with the federal and provincial governments, and that continues to be the case, as with other major municipalities in Canada.

    After we complete the investment of $2.1 billion dedicated to the Confederation Line, we can afford $3 billion between now and 2031.

    That is the envelope for growth-related transit projects that we can afford in our conservative financial plan.

    But light rail improvements are not the only public transit infrastructure that we need to include in our budgeting.

    Over the next ten years, we will service new growth with $500 million in bus transit improvements in the form of new Transitway links and priority lanes.

    As I mentioned earlier, these links will no longer be dependent on receiving two-thirds funding from senior orders of government.

    We want to move ahead with these projects without further delay.

    Today I am pleased to present to you a plan for Stage 2 that can, I believe, form a rally point for all levels of government and for our own Council.

    This period in our city’s development is similar to the build out of the Transitway decades ago – a time of major investment for decades of reward.

    We want to gain the full benefit of LRT to enable a shift to a more sustainable transportation future.

    And through this Stage 2 plan…

    We will shift LRT up an entire generation.

    Building on the Confederation Line…

    I am pleased to announce today that the Stage 2 plan moves decisively to spread the benefit of Light Rail to the west, east and south.

    Together.

    map_stage2_bil

     

    This plan responds to Council’s direction and desire to build on the work we are doing now to dramatically improve the O-Train.

    I want to take you through each segment of Stage 2 in some detail.

    First, let’s look west and southwest.

    We’ve put a lot of time and energy into working with the community to find a route through to the west.

    The Richmond Underground will provide the rapid rail transit extension that we need.

    I want to thank Councillors Hobbs, Taylor and Egli for their strong leadership here.

    Making good use of our existing Transitway infrastructure, we will continue with electric light rail west of Tunney’s Pasture, where it will stop at upgraded versions of the stations we have today at Westboro and Dominion.

    From Dominion Station, the route will travel down the former CP rail corridor to quickly enter the cover of a tunnel to maintain access to the waterfront.

    We will bury and enclose the line near residents to ensure continued views and quiet enjoyment for homeowners along the corridor.

    And we will continue to work with the NCC to meet their requirements.

    This underground section will continue to a new open-air station just past Cleary.

    We have moved the station at Cleary slightly to the west and reduced its footprint to take into account input during our public meetings.

    From Cleary, the tunnel will descend gradually before crossing under Richmond Road, stopping at a second new open-air station at New Orchard, before traveling underground to Lincoln Fields.

    These two stations will provide new, convenient rapid transit service for west end residents.

    And perhaps most significantly, the Byron Linear Park will be protected from one end to the other.

    Some residents may say “why should we pay for that to be underground?”

    The answer is clear to me…

    We have to move through some very well established neighbourhoods here… and we need to do right by them.

    Light rail needs to be implemented in a way that enhances the existing character of those communities and benefits the residents and businesses there with far better transit access.

    From Lincoln Fields, I support moving quickly to deploy light rail west to Bayshore Shopping Centre and south to Baseline.

    Beginning with the south route, we will travel from Lincoln Fields under the Queensway, through a new station at Iris, to Baseline.

    Finally, we will bring the significant investment we already have in Baseline Station into service as we link Algonquin College, Carleton, the University of Ottawa, and La Cité.

    Now that’s an education powerhouse in the capital connected by rapid transit.

    And with the quick and frequent feeder bus service to the growing southwest Barrhaven community, down the already built dedicated Transitway, we will dramatically improve the transit experience for the fastest growing areas of the city and make it more affordable to carry more passengers.

    I want to thank Councillors Harder and Desroches for the advancing of increased service for their constituents.

    Now let’s look at the route from Lincoln Fields to Bayshore.

    There had been a busway planned for this section that would have faced near immediate demand for conversion to LRT.

    So instead of building for buses – looking at wasteful and disruptive conversion costs – and then going to rail, we are going to leapfrog to better transit for the west now.

    From Lincoln Fields, the route to Bayshore will split off to the south of Woodroffe High School from the line to Baseline that I just described.

    The train then runs through an expanded Connaught Tunnel past the existing Pinecrest Bus Garage.

    Thanks here again to Councillor Taylor for improving on the plan to account for the concerns of people in the Roman Avenue area.

    As with the Richmond Underground, working with the community we’ve found better solutions.

    From there the line will run onto the City right-of-way just north of the Queensway, stopping at a new Queensview station.

    This will serve the area’s residents and businesses, including Hewlett Packard and the Leon’s.

    This will also include a new walking bridge across the Queensway, which will connect the rail line to the Pinecrest Shopping Complex, the new Ikea to the south, and other nearby businesses.

    From Queensview, the route makes an additional stop on the west side of Pinecrest to serve the residential communities north and south before continuing on to Bayshore Shopping Centre.

    Once at Bayshore, the line will tie-in to the bus network infrastructure where a new Bayshore-to-Moodie dedicated busway will connect with the existing west BRT and the new March to Terry Fox busway I described earlier.

    This will provide continuous rapid transit to Kanata, something advocated by Councillors Hubley and Wilkinson.

    Now… to the south.

    Building on the $59 million improvement underway now to increase service, we will make further enhancements to the O-Train to serve communities in the south and growing ridership along the line.

    We will open the system to serve more areas by adding stations at Gladstone, Walkley Road, and South Keys, creating more convenient options for people to make transit a part of their day.

    And we will extend the line to Leitrim and Bowesville and provide expanded park and ride facilities to support commuting from Barrhaven and Riverside South to those stations.

    This will be a full grade-separated route with new structures to cross Leitrim, Lester and Bowesville roads.

    My thanks to Councillors Deans and Desroches for their strong push for further expansion south now, not later.

    And to Councillors Hobbs, McRae and Holmes for underscoring the importance of added stations to serve the residents along the O-Train line more directly.

    Finally…to the east.

    We will complete the conversion of the light rail line from Blair Station through to Place D’Orleans.

    Four new stations will be put in place: at St. Joseph, Jeanne D’Arc, Orleans Drive, and Place d’ Orleans.

    The construction of LRT along our existing highway alignment will also free up the existing lanes used for buses today.

    During the EA process we will look at how to use these former bus lanes to expand the highway for HOV lanes.

    Currently, 60 per cent of Orleans residents who work downtown use transit each weekday.

    That takes a lot of articulated and double decker buses we won’t have to fill with diesel or replace at the end of the decade if we get moving more quickly.

    But this is not just about daily commutes to downtown.

    When complete, 90 per cent of Orleans’ residents will live within five kilometers of light rail.

    And moving quickly will be a game changer for renewed economic growth in the east end as rail will open access and tie the east to the downtown and beyond.

    Councillors Blais, Monette, Tierney and Bloess have been real leaders for balanced economic development.

    The east has suffered over the last ten years with shifting federal employment patterns.

    We want to work with the Government of Canada to locate jobs in the east and to attract employers there to support balanced growth.

    Bringing the benefits of light rail east to Place d’Orleans will make that difference.

    Last month, we announced a major employment complex has been attracted to north Orleans.

    I believe Stage 2 will give us what we need as a team to make the case for bringing more federal and private sector jobs to Orleans.

    In sum what I have just laid out can be built for less than $2.5 Billion.

    This includes:

     – $400 million to get to Lincoln Fields from Bayshore
    – $980 million to get to Baseline from Tunney’s Pasture
    – $500 million to finish getting to Orleans
    – $100 million for further O-train enhancements; and
    – $500 million for the trains and expanded storage facilities needed to serve the full system.

    This should be a package we can all agree to get a move on.

    Stage 2 of light rail will build on the benefits of the Confederation Line for our city as a whole.

    We could go slowly and build each segment of the network over a protracted period of time, suffering wasteful and disruptive conversions along the way…

    Or we can move ahead and use public transit to help define how we grow.

    We could muddle through paying for another twenty or thirty years of long-haul buses…

    Or we can make the most of LRT by completing the network to realize the benefits more quickly.

    Instead of phasing these extensions to 2031, what I am proposing as Stage 2 is a single LRT project.

    A project that will bring rail west to Bayshore and Baseline… south to Bowesville… and east to Orleans.

    It would all be done together… well in advance of any previous schedule this city has ever seen.

    That means if our federal and provincial partners come to the table with their share of funds, we could have this impressive system up and running within five years of completing the Confederation Line – as early as 2023.

    Like all major municipalities with large transit projects, these are plans we can only undertake together.

    We all know the old saying:

    When you stand still, you fall behind.

    The leading municipalities in this country are ready with clear plans for cost sharing of needed transit improvements.

    Let me be clear, coming together with a strong plan and a united voice is the way we will succeed.

    Together… with our partners Ontario and Canada, we need to get ahead of growth and use transit planning, as so many other cities around the world have done, to develop in a healthy way.

    Together, we can move up light rail an entire generation.

    By completing this, we will add 35 kilometers of new rail and 19 new stations that will improve public transit, attract new customers and contain costs.

    We’ll have a system that can handle the growth instead of struggling with increasingly crowded buses and increasingly divisive budget battles.

    We will have a system that is reliable and on-time because the main spines will be dedicated and freed from competing with traffic.

    We can replace most of our articulated bus fleet with more efficient trains that will be quieter and far less polluting.

    We can get more than 450,000 buses a year off the Sir John A MacDonald Parkway.

    Best of all, our city will be connected with a light rail transit spine from east to west to south.

    As our community ages, it will help to keep our citizens out and about.

    Big celebrations that our capital city hosts, like Canada Day, will have a lot less transportation frustration.

    Beyond connecting our post secondary institutions, as I’ve mentioned, the network will stretch from our fastest growing communities in the east, west and south.

    It will connect six major shopping malls, many hotels from the Delta to the Hampton to the Westin, not to mention our libraries, arts facilities and recreational facilities.

    All connected with an upgraded transit experience—safe, modern, comfortable and accessible light rail—that will help define for the better how we grow and develop as a healthy urban municipality.

    Let’s move forward…

    East, west, south…

    Together.

    And let’s define our own success as a community.

    Thank you.